PROJECT SUMMARY
Earthworks for Terminal 3 chemical storage yard facility (30,000 sq m), including soil stabilization, drainage, services and Combi-lift service building. Works also included groundworks for Building F warehouse (5,325 sq m) including substructures, drainage, services and external works

CLIENT
Flynn MC on behalf of Chemco Ireland Ltd.

Main Contractor:

Services:

Earthworks and soil stabilization for Terminal 3 chemical storage concrete yard facility | Substructures for combi shelter service building and Building F warehouse | Surface water contained drainage system | Underground services for watermain | Fire main and ducting

Design Team:

Architect & Engineer: RMcG Services Ltd.

Key Features:

Strip topsoil and dispose in stockpiles on site (63,500m2)

Reduce level excavation, disposal on site, double handling & placing on site, soil stabilization, compaction, CBR testing, hardcore filling & blinding (46,640m3)

Installation of surface water system ranging from 150mm to 600mm diameter pipework, including contained drainage PE SDR17 welded pipework, fittings and valves, with attenuation tank, capable of containing a chemical spillage (2km)

Install underground ducting, ESB, comms, site lighting and 60nr access chambers (10km)

Groundworks for Building F warehouse, including bulk dig, foundations, prep floors, drainage & services (5,325m2)

Programme: 40 weeks